FFYs 2023-27 Transportation Improvement Program (TIP) Amendment Six

 

This is a complex table that has not been optimized for screen–reading software. If you would like to request this table in a alternative format, please contact the Central Transportation Planning Staff (CTPS) via email at publicinfo@ctps.org Overall Changes in Funding in TIP
Project Proposed Change Explanation Section/Funding Source From To Difference
FFY 2023 Highway Funds            
610919: Lynn–Nahant–Northern Strand Extension
Cost Increase The funding for this project is being increased to reflect the final cost estimate resulting from the final design of the project. State Highway: CMAQ, HSIP-VUS $9,363,750 $10,939,360 $1,575,610
S12640: Framingham– High Risk At-Grade Railroad Crossing Countermeasures on Route 126
New Start Year This project is being accelerated from the FFY 2024 Statewide Highway Program into the FFY 2023 program. The project's budget remains the same. State Highway: Railroad Crossings Hazard Elimination, Railroad Crossings Protective Devices $0 $3,500,000 $3,500,000
FFY 2023 Transit Program            
MBTA011496: Salem – Retrofit of an Existing Ferry New Project This project programs a USDOT Passenger Ferry Grant program grant to retrofit an existing ferry for the City of Salem. Transit Program: USDOT Passenger Ferry Grant program
N/A $4,000,000 $4,000,000
FFY 2023 Regional Target Program            
S12705: Lynn Station Improvements Phase II
Funding Source Adjustment The funding source for these projects has been adjusted based on state guidance. The overall budget for these projects remains the same. Regional Target Highway: STBG $13,600,000 $13,600,000 $0
S12706: Forest Hills Improvement Project Funding Source Adjustment The funding source for these projects has been adjusted based on state guidance. The overall budget for these projects remains the same. Regional Target Highway: STBG $6,400,000 $6,400,000 $0
FFY 2024 Highway Funds            
S12640: Framingham– High Risk At-Grade Railroad Crossing Countermeasures on Route 126
New Start Year This project is being accelerated from the FFY 2024 Statewide Highway Program into the FFY 2023 program. The project's budget remains the same. State Highway: Railroad Crossings Hazard Elimination, Railroad Crossings Protective Devices $3,500,000 $0 -$3,500,000

CMAQ = Congestion Mitigation and Air Quality Improvement. FFY= Federal Fiscal Year. HSIP-VUS= Highway Safety Improvement Program - Vulnerable User Safety. MBTA= Massachusetts Bay Transportation Authority. STBG = Surface Transportation Block Grant Program. USDOT = United States Department of Transportation.

*The MBTA, Cape Ann Transportation Authority (CATA), and MetroWest Regional Transit Authority (MWRTA), which are Federal Transit Administration (FTA) Section 5307(c) applicants, have consulted with the MPO and concur that the public involvement process adopted by the MPO for the development of the TIP satisfies the public hearing requirements that pertain to the development of the Program of Projects for regular Section 5307, Urbanized Area Formula Program, grant applications, including the provision for public notice and the time established for public review and comment.