Project Identification

Unified Planning Work Program (UPWP) Classification

Agency and Other Client Transportation Planning Studies and Technical Analyses

Project Number 13809

Client

Massachusetts Department of Transportation (MassDOT) Highway Division
Client Supervisor: Mike O’Dowd

Project Supervisors

Principal: Rosemary McCarron
Manager: Ben Dowling

Funding Source

MassDOT On-Call Support Contract

Schedule and Budget

Schedule: Four months from notice to proceed

Budget: $116,039

Schedule and budget details are shown in Exhibits 1 and 2, respectively.

Relationship to MPO Work

This studyis supported in full with non-MPO funding. Committing MPO staff to this project will not impinge on the quality or timeliness of MPO-funded work.

Background

This work program will expand upon prior Central Transportation Planning Staff (CTPS) work modeling the Allston Multimodal Project. The project is expected to dramatically improve livability and connectivity for residents of the Allston neighborhood of Boston. It will enhance regional mobility through improvements to Interstate 90 (I-90) and its abutting interchange and create a new stop on the Worcester/Framingham commuter line, to be known as West Station.

CTPS provided support for this project in 2018 and 2020. MassDOT and its project team are currently developing a Supplemental Draft Environmental Impact Report and have requested that CTPS produce travel-demand forecasts to help understand the transportation impacts and opportunities of the project. 

Objectives

CTPS will support MassDOT and the project team by using CTPS’s regional travel demand model set to produce data on highway volumes, transit volumes, and mode splits in the study area for opening- and forecast-year scenarios.

Work Description

As described in Tasks 1 through 4 below, CTPS will estimate roadway volumes for I-90, the Allston Interchange, and the surface roadway network surrounding the interchange. This is a Phase 1 work program and it is anticipated that additional phases will follow.

Task 1  Model Setup

CTPS will prepare the regional travel demand model for use in this study.

Products of Task 1

A regional travel demand model set which is suitable for the study

Task 2  Model One Forecast-Year Scenario

CTPS will model the Forecast-Year No-Build scenario to include a new split zone for Transportation Analysis Zone (TAZ) 246 and reconfigured centroid connectors to produce more realistic highway assignments for TAZ 246 and the new TAZ. The No-Build scenario will also incorporate expected changes to transit operations in the horizon year, including a spring 2023 commuter rail schedule and Bus Network Redesign routing for specific routes to be identified by the project team. This No-Build scenario will be compared to an appropriate base-year scenario.

Products of Task 2

Task 3  Model One Opening-Year Scenario

CTPS will model the Opening-Year No-Build scenario to support the project team and its opening-year analysis.

Product of Task 3

CTPS will provide the project team with the same set of outputs and analysis listed under Task 2 above, except for volume plots.

Task 4  Project Coordination

CTPS will coordinate with the project team throughout the study, which is expected to result in the submission of an environmental filing.

Products of Task 4

Attendance at various internal team meetings

 

Exhibit 1 ESTIMATED SCHEDULE I-90 Allston Multimodal Modelling--Phase 1

Task Month
1 2 3 4 5
1.
Model Setup
From Month 1, Week 1 to Month 1, Week 4.
2.
Model One Forecast Year Scenario
From Month 1, Week 3 to Month 4, Week 1.
3.
Model One Opening Year Scenario
From Month 4, Week 2 to Month 5, Week 1.
4.
Project Coordination
From Month 1, Week 1 to Month 5, Week 1.

 

Exhibit 2 ESTIMATED COST I-90 Allston Multimodal Modelling--Phase 1

Direct Salary and Overhead

$116,039
Task Person-Weeks Direct Salary Overhead (119.34%) Total Cost
M-1 P-4 P-2 Total
1.
Model Setup
0.0 2.0 1.0 3.0 $4,837 $5,772 $10,608
2.
Model One Forecast Year Scenario
0.0 9.0 9.0 18.0 $27,952 $33,358 $61,310
3.
Model One Opening Year Scenario
0.0 3.0 4.0 7.0 $10,692 $12,760 $23,452
4.
Project Coordination
2.0 1.5 2.0 5.5 $9,423 $11,245 $20,669
Total
2.0 15.5 16.0 33.5 $52,904 $63,135 $116,039

Other Direct Costs

$0

TOTAL COST

$116,039
Funding
MassDOT On-Call Support Contract

 

 

The Boston Region Metropolitan Planning Organization (MPO) operates its programs, services, and activities in compliance with federal nondiscrimination laws including Title VI of the Civil Rights Act of 1964 (Title VI), the Civil Rights Restoration Act of 1987, and related statutes and regulations. Title VI prohibits discrimination in federally assisted programs and requires that no person in the United States of America shall, on the grounds of race, color, or national origin (including limited English proficiency), be excluded from participation in, denied the benefits of, or be otherwise subjected to discrimination under any program or activity that receives federal assistance. Related federal nondiscrimination laws administered by the Federal Highway Administration, Federal Transit Administration, or both, prohibit discrimination on the basis of age, sex, and disability. The Boston Region MPO considers these protected populations in its Title VI Programs, consistent with federal interpretation and administration. In addition, the Boston Region MPO provides meaningful access to its programs, services, and activities to individuals with limited English proficiency, in compliance with U.S. Department of Transportation policy and guidance on federal Executive Order 13166.

The Boston Region MPO also complies with the Massachusetts Public Accommodation Law, M.G.L. c 272 sections 92a, 98, 98a, which prohibits making any distinction, discrimination, or restriction in admission to, or treatment in a place of public accommodation based on race, color, religious creed, national origin, sex, sexual orientation, disability, or ancestry. Likewise, the Boston Region MPO complies with the Governor's Executive Order 526, section 4, which requires that all programs, activities, and services provided, performed, licensed, chartered, funded, regulated, or contracted for by the state shall be conducted without unlawful discrimination based on race, color, age, gender, ethnicity, sexual orientation, gender identity or expression, religion, creed, ancestry, national origin, disability, veteran's status (including Vietnam-era veterans), or background.

A complaint form and additional information can be obtained by contacting the MPO or at http://www.bostonmpo.org/mpo_non_discrimination. To request this information in a different language or in an accessible format, please contact

Title VI Specialist
Boston Region MPO
10 Park Plaza, Suite 2150
Boston, MA 02116
civilrights@ctps.org

By Telephone:
857.702.3700 (voice)

For people with hearing or speaking difficulties, connect through the state MassRelay service:

  • Relay Using TTY or Hearing Carry-over: 800.439.2370
  • Relay Using Voice Carry-over: 866.887.6619
  • Relay Using Text to Speech: 866.645.9870

For more information, including numbers for Spanish speakers, visit https://www.mass.gov/massrelay.