Project | Proposed Change | Explanation | Section/Funding Source | From | To | Difference |
FFY 2023 Highway Funds | ||||||
610919: Lynn – Nahant – Northern Strand Extension |
Cost Increase | Explanation forthcoming from MassDOT | State Highway: CMAQ, HSIP-VUS | $9,363,750 | $10,939,360 | $1,575,610 |
FFY 2023 Transit Program | ||||||
MBTA011496: Salem – Retrofit of an Existing Ferry | New Project | This project programs a USDOT Passenger Ferry Grant program grant to retrofit an existing ferry for the City of Salem. | Transit Program: USDOT Passenger Ferry Grant program |
N/A | $4,000,000 | $4,000,000 |
FFY 2023 Regional Target Program | ||||||
S12705: Lynn Station Improvements Phase II |
Funding Source Adjustment | The funding source for these projects has been adjusted based on state guidance. The overall budget for these projects remains the same. | Regional Target Highway: STBG | $13,600,000 | $13,600,000 | $0 |
S12706: Forest Hills Improvement Project | Funding Source Adjustment | The funding source for these projects has been adjusted based on state guidance. The overall budget for these projects remains the same. | Regional Target Highway: STBG | $6,400,000 | $6,400,000 | $0 |
CMAQ = Congestion Mitigation and Air Quality Improvement. FFY= Federal Fiscal Year. HSIP-VUS= Highway Safety Improvement Program - Vulnerable User Safety. MBTA= Massachusetts Bay Transportation Authority. STBG = Surface Transportation Block Grant Program. USDOT = United States Department of Transportation.
*The MBTA, Cape Ann Transportation Authority (CATA), and MetroWest Regional Transit Authority (MWRTA), which are Federal Transit Administration (FTA) Section 5307(c) applicants, have consulted with the MPO and concur that the public involvement process adopted by the MPO for the development of the TIP satisfies the public hearing requirements that pertain to the development of the Program of Projects for regular Section 5307, Urbanized Area Formula Program, grant applications, including the provision for public notice and the time established for public review and comment.