Overall Changes in Funding in TIP | ||||||
Project | Proposed Change | Explanation | Section/Funding Source | From | To | Difference |
FFY 2023 Statewide Highway | ||||||
608208: Quincy–Milton–Boston—Interstate Maintenance and Related Work on Interstate 93 | Source Change | The funding sources for this project have been adjusted to reflect the amount of bridge preservation and maintenance work in the contract. The overall budget remains the same. | State Highway: HIP-BR, NHPP |
$37,591,924 | $37,591,924 | $0 |
FFY 2023 Transit Program | ||||||
RTD0010589: CATA—Revenue Vehicle Replacement | Correction | Budget adjusted to accurately reflect the total federal funding share as identified by the project. | FTA Section 5307 | $870,000 | $965,000 | $95,000 |
CATA = Cape Ann Transportation Authority. FFY = Federal Fiscal Year. FTA = Federal Transit Administration. HIP-BR = Highway Investment Program - Bridge. NHPP = National Highway Performance Program. |