Central Transportation Planning Staff |
Draft SFY 2022 Revenue Projections |
|
|
Contract |
SFY2022 |
CTPS Contract Number |
Description |
Budget |
Direct Costs |
Labor and Overhead |
Start Date |
End Date |
Salary & Overhead |
Direct Costs |
Total |
3C PL & 5303 |
|
|
|
|
|
|
|
|
|
C2021 |
3C PL, 5303, and MD 5303 FFY 2021 |
$4,803,935 |
$85,000 |
$4,718,935 |
10/1/20 |
9/30/21 |
$1,401,351 |
$27,000 |
$1,428,351 |
C2022 |
3C PL, 5303, and MD 5303 FFY 2022 |
$4,615,994 |
$92,000 |
$4,523,994 |
10/1/21 |
9/30/22 |
$3,405,812 |
$91,350 |
$3,497,162 |
|
|
|
|
|
|
MPO Subtotal |
$4,807,163 |
$118,350 |
$4,925,513 |
MassDOT/Other |
|
|
|
|
|
|
|
|
|
C1321.2 |
SPR Projects 2020 - 2021 |
$507,000 |
$600 |
$506,400 |
10/1/20 |
12/31/21 |
$215,000 |
$600 |
$215,600 |
C1322 |
SPR Projects 2021 - 2022 |
$500,000 |
$0 |
$500,000 |
10/1/21 |
9/30/22 |
$375,000 |
|
$375,000 |
C0730 |
On-Call Modeling Support |
$850,000 |
$0 |
$850,000 |
6/1/18 |
3/31/22 |
$100,000 |
|
$100,000 |
TBD |
On-Call Modeling Support FY22 |
$300,000 |
$0 |
$300,000 |
1/1/22 |
9/30/22 |
$300,000 |
|
$300,000 |
C0731 |
MassDOT Title VI Program |
$95,000 |
$0 |
$95,000 |
2/1/20 |
1/31/22 |
$30,000 |
|
$30,000 |
C0732 |
Silverline Extension Alternatives |
$115,000 |
$0 |
$115,000 |
9/1/20 |
6/30/22 |
$55,000 |
|
$55,000 |
C0733 |
Wellington Circle Study |
$108,664 |
$0 |
$108,664 |
1/8/21 |
12/31/21 |
$75,000 |
|
$75,000 |
|
|
|
|
|
|
MassDOT Subtotal |
$1,150,000 |
$600 |
$1,150,600 |
MBTA |
|
|
|
|
|
|
|
|
|
C0938 |
AFC 2.0 Equity Analysis |
$76,972 |
$0 |
$76,972 |
1/15/21 |
12/31/23 |
$55,000 |
|
$55,000 |
C0931 |
MBTA 2020 Triennial Title VI Report |
$139,632 |
$500 |
$139,132 |
7/26/19 |
12/31/21 |
$38,000 |
|
$38,000 |
C0935 |
MBTA 2021 NTD |
$123,317 |
$200 |
$123,117 |
7/1/20 |
12/31/21 |
$14,000 |
|
$14,000 |
TBD |
MBTA 2022 NTD |
$127,288 |
$200 |
$127,088 |
7/1/21 |
12/31/22 |
$96,587 |
$150 |
$96,737 |
TBD |
MBTA 2022 Title VI Monitoring |
$77,000 |
$500 |
$76,500 |
7/26/19 |
12/31/21 |
$39,300 |
$500 |
$39,800 |
TBD |
MBTA Mapping Support |
$18,000 |
$0 |
$18,000 |
7/1/21 |
6/30/24 |
$6,000 |
|
$6,000 |
C0930 |
MBTA Transit Service Data Collection |
$540,000 |
$1,725 |
$538,275 |
7/1/19 |
11/30/22 |
$180,000 |
|
$180,000 |
C0934 |
Prioritization of Dedicated Bus Lanes |
$82,245 |
$0 |
$82,245 |
6/10/20 |
7/31/21 |
$8,000 |
|
$8,000 |
C0918 |
Rider Oversight Committee Support III |
$24,500 |
$0 |
$24,500 |
7/1/17 |
12/31/21 |
$3,000 |
|
$3,000 |
TBD |
Rider Oversight Committee Support IV |
$24,500 |
$0 |
$24,500 |
1/1/22 |
12/31/25 |
$3,000 |
|
$3,000 |
C0925 |
Service Equity Analysis Support |
$115,000 |
$0 |
$115,000 |
6/1/18 |
3/31/21 |
$60,000 |
|
$60,000 |
TBD |
SFY 2023 Fare Equity Analysis |
$20,000 |
$0 |
$20,000 |
8/1/21 |
6/30/22 |
$20,000 |
|
$20,000 |
|
|
|
|
|
|
MBTA Subtotal |
$522,887 |
$650 |
$523,537 |
Other |
|
|
|
|
|
|
|
|
|
TBD |
Anticipated Other Contracts |
$80,000 |
$0 |
$80,000 |
7/1/21 |
6/30/22 |
$80,000 |
|
$80,000 |
|
|
|
|
|
|
Other Subtotal |
$80,000 |
$0 |
$80,000 |
|
|
|
|
|
|
Total |
$6,560,050 |
$119,600 |
$6,679,650 |