WORK PROGRAM
Updates to Express Highway Volume Charts
OCTOBER 4, 2018
The Boston Region Metropolitan Planning Organization (MPO) votes to approve this work program.
Boston Region MPO Planning Studies and Technical Analyses
Boston Region MPO
Principal: Scott Peterson
Manager: Benjamin Krepp
MPO Planning Contract #105757 and MPO §5303 Contract #102694 and subsequent §5303 contract
Schedule and budget details are shown in Exhibits 1 and 2, respectively.
The Boston Region MPO elected to fund this study with its federally allocated metropolitan planning funds during federal fiscal year (FFY) 2019. The work completed through this study will address the following goal area established in the MPO’s Long-Range Transportation Plan: capacity management and mobility.
The Central Artery/Third Harbor Tunnel (CA/T) Project dramatically changed the configuration of the regional express highway system and associated arterial roadways in the Boston region. In order to support the numerous planning efforts undertaken in response to the new regional traffic flow patterns, the former Central Area Group of the Boston Region MPO developed an integrated set of express highway volume charts. These charts initially focused on the CA/T project area, but were gradually extended to cover express highways throughout the MPO region. Figure 1 shows one page of this chart system, which depicts AM peak-period traffic on the Southeast Expressway.
The data in these charts have been useful in studies conducted by MPO staff, and are requested frequently by members of the public. These charts were developed and exist only in portable document format (PDF). They may be viewed and downloaded from the MPO website in that form; however, the underlying data are not available in comma-separated value (CSV) (spreadsheet) format.
The work program presented here is a for a pilot project to develop up-to-date balanced volume data and to make it available for viewing online in graphical and tabular forms, as well as available for downloading in CSV format. The pilot project will focus on two routes: 1) Route 3 between Braintree and the southern border of the MPO region in Marshfield; and 2) Interstate 93 between the northern border of the MPO in Wilmington and Braintree. MassDOT has recently collected traffic count data for Route 3; and is planning to do so for Interstate 93 in fall 2018 or spring 2019. If the new I-93 counts are not available by late-spring 2019, then recently collected count data for I-495 will be used in its place.
Historical balanced volume data from 1999–2000 and 2010–2011 exists for these routes. The work program presented here will also make this historical data available in the same presentation framework used for the newly developed balanced volume data, which would allow historical and newly developed data to be compared.
MPO staff will identify currently available traffic count data and coordinate with MassDOT to obtain additional traffic count data as necessary. Project staff and tabulators will conduct selective counts of visibly accessible ramps on the Central Artery to corroborate and supplement MassDOT counts, as appropriate.
Project staff will develop one or more online methods of presenting balanced volume data. The usability of these techniques will be evaluated in consultation with other MPO staff members who frequently use balanced volume data in MPO projects. Project staff will consider implementation alternatives, and will recommend the technical approach to be used in the final deliverable.
Suite of graphical elements and technical tools for presenting balanced volume data
MPO staff will develop average weekday daily traffic (AWDT) and hourly peak-period balanced traffic volumes for key express highway sections where sufficient new data is available.
Updated balanced volume data in CSV format
All historical balanced volume data exists only in the form of PDF charts. In order to make this data available to be rendered using modern on-line graphical techniques, MPO temp staff will encode this data in CSV format.
CSV files encoding historical balanced volume data for Interstate 93 and Route 3 south from 1999-2000 and 2010-2011
Using the techniques developed in Task 2, MPO staff will develop an interactive online tool to render the up-to-date balanced volume data developed in Task 3 and the historical balanced volume data encoded in Task 4 in graphical and tabular formats, and make the data available for download in CSV format.
Web application hosted on the MPO website that would make newly developed and historical balanced volume data available in graphical and tabular formats that will enable planners and engineers to better understand congestion and traffic volumes in the region
MPO staff will write a TransREPORT article about the interactive balanced volumes tool, and will document the methodology used to develop the new set of balanced volumes and the interactive application. MPO staff will present the interactive online tool developed in Task 5 to the MPO.
TransREPORT article, internal documentation, presentation to the MPO
Task |
Month | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | |
1.
Obtain Traffic Count Data |
A
|
||||||||||
2.
Develop Interactive Graphics Techniques |
B
|
||||||||||
3.
Develop Updated Balanced Volumes |
C
|
||||||||||
4.
Encode Historical Balanced Volume Data |
D
|
||||||||||
5.
Develop Interactive Online Tool |
E
|
||||||||||
6.
Prepare Documentation and Presentation |
F
|
Task |
Person-Weeks | Direct Salary |
Overhead (99.00%) |
Total Cost |
||||
---|---|---|---|---|---|---|---|---|
M-1 | P-5 | P-4 | Temp | Total | ||||
1.
Obtain Traffic Count Data
|
0.0 | 2.0 | 0.0 | 2.0 | 4.0 | $4,950 | $4,900 | $9,850 |
2.
Develop Interactive Graphics Techniques
|
0.0 | 4.0 | 0.0 | 0.0 | 4.0 | $7,862 | $7,783 | $15,644 |
3.
Develop Updated Balanced Volumes
|
0.0 | 4.0 | 0.0 | 0.0 | 4.0 | $7,862 | $7,783 | $15,644 |
4.
Encode Historical Balanced Volume Data
|
0.0 | 0.4 | 0.0 | 2.1 | 2.5 | $1,837 | $1,819 | $3,657 |
5.
Develop Interactive Online Tool
|
0.0 | 7.0 | 1.0 | 0.0 | 8.0 | $15,167 | $15,016 | $30,183 |
6.
Prepare Documentation and Presentation
|
0.6 | 2.0 | 0.0 | 0.0 | 2.6 | $5,036 | $4,985 | $10,021 |
Total
|
0.6 | 19.4 | 1.0 | 4.1 | 25.1 | $42,713 | $42,286 | $85,000 |