Overall Changes in Funding in TIP |
Project |
Proposed Change |
Explanation |
Section/Funding Source |
From |
To |
Difference |
604804; Reading - Resurfacing and Related Work on Route 28 (Main Street) |
DECREASE COST |
Cost decrease due to final design. |
Section 2A/Non-Interstate Pavement |
$7,424,556 |
$6,063,543 |
($1,361,013) |
608008; Saugus - Resurfacing and Related Work on Route 1 |
INCREASE COST |
Cost increase due to final design. |
Section 2A/Non-Interstate Pavement |
$9,812,880 |
$11,076,010 |
$1,263,130 |
606381; Cambridge - Arlington - Belmont - Lexington - Highway Lighting Repair and Maintenance on Route 2 |
INCREASE COST |
Cost increase resulting from changes in scope:
- Inclusion of Roadway Lighting on the Alewife Station Access Road.
- Relocation of some of the Roadway Lighting on Route 2 from the outside edges of Route 2 to the median.
- Installation of lighting at the Dow Street underpass.
- Inclusion of ITS cameras and components. |
Section 1B/Other Federal Aid (Earmark)
Section 2A/Safety Improvements |
$14,178,273 |
$15,714,202 |
$1,535,929 |
606632; Hopkinton-Westborough- Bridge Replacement, Fruit St. over CSX and Sudbury River |
REMOVE PROJECT |
Project advanced to 75% design; some design and environmental concerns resulted in the need for additional design and review time. |
Section 2A/Bridge Program/Off-System |
$11,465,706 |
$0 |
($11,465,706) |