Memorandum

Date      October 19, 2017

TO           Boston Region Metropolitan Planning Organization

FROM     Karl H. Quackenbush, Executive Director

RE           Work Program for Travel Alternatives to Regional Traffic Bottlenecks

Action Required

Review and approval

Proposed Motion

That the Boston Region Metropolitan Planning Organization (MPO) votes to approve the work program for Travel Alternatives to Regional Traffic Bottlenecks presented in this memorandum

Project Identification

Unified Planning Work Program Classification

Planning Studies and Technical Analysis

CTPS Project Number

13285

Clients

Boston Region Metropolitan Planning Organization

CTPS Project Supervisors

Principal: Mark Abbott

Manager: Ryan Hicks

Funding

MPO Planning Contract #101725

MPO §5303 Contract #98873 and subsequent MPO §5303 contract

Impact on MPO Work

This is MPO work and will be carried out in conformance with the priorities established by the MPO.

Background

Of all of the important activities that the Boston Region MPO staff performs for its member communities, one of the most important is the development of the Congestion Management Process (CMP). In addition, the CMP is required by federal law. The main goal of the CMP is to identify recurring congestion during the AM and PM peak period. The Boston region has several unique characteristics that stand out from other metropolitan areas nationally:

As a result of these unique characteristics, the Boston region may experience congestion outside of the traditional peak periods and at locations that are not necessarily leading to a central business district. This study would go beyond the CMP requirements and determine locations and times that traffic congestion is occurring outside of the peak period. The anticipated result of this project is to provide a handbook of strategies to identify and mitigate nonrecurring congestion.

Objective

The objective for this project is to identify nonrecurring automobile and roadway freight congestion patterns on freeways and major arterials near activity centers in the Boston region, and to recommend strategies to alleviate the congestion. Nonrecurring congestion is typically caused by alternative events, which are defined as sporting events, concerts, festivals, construction, inclement weather, and holidays.

This project aims to achieve two related objectives that are stated in the Boston Region MPO Long-Range Transportation Plan (LRTP):2 1) Support community-based and private-initiative services and programs to meet last-mile, reverse commute, and other nontraditional transit/transportation needs, including those of the elderly and persons with disabilities and 2) respond to the mobility needs of the 25- to 34-year-old workforce (since these demographics are both a significant share of the Boston region’s population and are commonly adversely affected by nonrecurring congestion). The reason that these objectives are emphasized is because objectives strive towards achieving the LRTP goals of Capacity Management/Mobility, which focuses on using existing capacity more efficiently, and increasing healthy transportation capacity and Economic Vitality, which focuses on ensuring that our transportation network provides a strong foundation for economic vitality.

Work Description

Task 1  Evaluate and Select Data Sources

The Boston Region MPO has access to several vehicle probe data sets that provide sufficient coverage for this project. One option is the 2015 INRIX data set, which contains extensive data about weekend and special events. Another option is the National Performance Management Research Data Set (NPMRDS), which is provided monthly to MPOs by the Federal Highway Administration (FHWA). The NPMRDS contains a subset of data that monitors freight traffic on roadways. A combination of data sets may be used for this project, if applicable. Other data sets that are accessible by the Boston MPO will be considered for inclusion with this project.

Products of Task 1

Task 2  Select Performance Measures

There are several CMP and roadway freight performance measures that are used to monitor the roadway network. These CMP performance measures have been in use by the Boston Region MPO for the last several years. In addition, the FHWA and the Boston Region MPO are showing an increasing presence of freight monitoring by using performance measures to monitor freight congestion. This freight presence is increasing as on-time delivery for freight transport becomes more important to the US economy.

Staff will select several CMP and roadway freight performance measures that will be used specifically to determine the duration, intensity, and variability of congestion at the selected locations. Performance measures that were created by the FHWA to monitor the National Highway System will also be considered for inclusion for this project.

Products of Task 2

Task 3  Identify Alternative Events

Alternative events that occur in the Boston region, both during the week and on weekends, will be identified, and their effects on congestion will be examined locally and regionally. Congested conditions at the time of the alternative events will be compared to traditional peak periods and free-flow periods. Possible alternative events include, but are not limited to, sporting events, concerts, festivals, construction, inclement weather, and holidays. Data for the times and locations of each of these events are readily available from various online sources.

Product of Task 3

Task 4  Determine Bottleneck Locations

The data set(s) that were selected in Task 1 will be used to determine the locations that have nonrecurring congestion or bottlenecks, using the performance measures selected in Task 2. This task will also determine the final number of locations to be analyzed for this project.

Product of Task 4

Task 5  Document Methodology, Findings, and Recommendations

The MPO staff will produce a final memorandum of the study’s tasks and products. This memorandum will have three sections documenting the locations, strategies, and recommendations for the nonrecurring congestion. Specific recommendations of strategies to alleviate the nonrecurring congestion will be included.

Product of Task 5

Estimated Schedule

It is estimated that this project will be completed 12 months after work commences. The proposed schedule, by task, is shown in Exhibit 1.

Estimated Cost

The total cost of this project is estimated to be $70,000. This includes the cost of 22.7 person-weeks of staff time, overhead at the rate of 105.66% percent. A detailed breakdown of estimated costs is presented in Exhibit 2.

KQ/MSA/rh

1 Denis M. McSweeney and Walter J. Marshall. “The prominence of Boston area colleges and universities. 2009. https://www.bls.gov/opub/mlr/2009/06/regrep.pdf (accessed October 4, 2017)

2“Charting Progress to 2040: A Long-Range Transportation Plan for the Boston Region”, 2015. http://www.ctps.org/lrtp (accessed October 4, 2017)

Exhibit 1
ESTIMATED SCHEDULE
Travel Alternatives to Regional Traffic Bottlenecks


Task
Month
1 2 3 4 5 6 7 8 9 10 11 12
1.
Evaluate and Select Data Sources
From month 1 to 3.
2.
Select Performance Measures
From month 3 to 4.5.
3.
Identify Alternative Events
From month 4.5 to 6.5.
4.
Determine Bottleneck Locations
From month 6.5 to 8.5.
5.
Document Methodology, Findings, and Recommendations
From month 8.5 to 13.
Deliverable
, delivered by Month 1

Exhibit 2
ESTIMATED COST
Travel Alternatives to Regional Traffic Bottlenecks

Direct Salary and Overhead

$70,000

Task
Person-Weeks Direct
Salary
Overhead
(105.66%)
Total
Cost
M-1 P-5 P-4 Total
1.
Evaluate and Select Data Sources
0.2 1.0 2.0 3.2 $5,060 $5,346 $10,406
2.
Select Performance Measures
0.0 0.0 1.5 1.5 $2,088 $2,207 $4,295
3.
Identify Alternative Events
0.2 0.2 2.0 2.4 $3,537 $3,737 $7,274
4.
Determine Bottleneck Locations
0.4 0.4 2.0 2.8 $4,289 $4,532 $8,821
5.
Document Methodology, Findings, and Recommendations
2.0 0.5 10.3 12.8 $19,062 $20,141 $39,204
Total
2.8 2.1 17.8 22.7 $34,037 $35,963 $70,000

Other Direct Costs

$0

TOTAL COST

$70,000
Funding
MPO Planning Contract #101725
MPO §5303 Contract #98873 and subsequent MPO §5303 contract