Proponent TIP ID Project Name / Description Programmed Year Design Status as of 3/6/17 Readiness Assessment (MassDOT) Total Target Funds
(2017-2021)
Other TIP Funds (2017-2021) Programmed Amount
(2017-2021) 
Revised or Current Project Cost Estimate Year of Expenditure (Inflated) Cost* Change in Project Cost Estimate**
Bedford, Billerica, and Burlington 29492 Middlesex Turnpike Improvements, Phase III 2017 Final Advertised  $6,604,906  $8,438,700  $15,043,606  $15,043,606  n/a   $-  
Needham and Wellesley 603711 Rehabilitation/Replacement of 6 Bridges on I-95 / Route 128 (Add-a-Lane - Contract V) 2017-2018 Final Advertised  $26,528,183  $-    $26,528,183  $26,528,183  n/a   $-  
Weymouth and Abington 601630 Reconstruction and widening on Route 18 (Main St.) 2017-2019 Final Advertised  $40,481,758  $27,930,510  $68,412,268  $68,412,268  n/a   $-  
Somerville and Medford 1570 Green Line Extension (Phase I) 2017-2021 n/a Advertised  $181,900,000  $-    $181,900,000  $181,900,000  n/a   $-  
Hingham   607309 Reconstruction and related work on Derby St. 2017 100% Submitted 2017  $4,927,769  $-    $4,927,769  $6,716,047  n/a   $1,788,278
Marlborough 604810 Reconstruction of Route 85 (Maple St.) 2017 75% Submitted 2017  $5,613,636  $-    $5,613,636  $5,773,824  n/a   $160,188
Woburn 604935 Reconstruction of Montvale Ave. 2017 75% Submitted 2017  $4,752,838  $-    $4,752,838  $4,672,893  n/a   $(79,945)
Hingham (MassDOT) 600518 Intersection improvements at Derby St., Whiting St. (Route 53) and Gardner St. 2018 75% Submitted 2018  $3,057,735  $-    $3,057,735  $2,844,392  n/a   $(213,343)
Newton and Needham 606635 Reconstruction of Highland Ave., Needham St., and Charles River bridge 2018 75% Submitted 2019  $15,464,292  $-    $15,464,292  $25,036,514  n/a   $9,572,222
Brookline 605110 Intersection and signal improvements at Route 9 and Village Square (Gateway East) 2018 25% Submitted 2019  $5,273,202  $-    $5,273,202  $7,000,834  n/a   $1,727,632
Southborough 604989 Reconstruction of Main St. (Route 30) 2018 75% Submitted 2018 (risk)  $7,281,248  $-    $7,281,248  $7,271,690  n/a   $(9,558)
Salem 608352 Canal Street Rail Trail Construction (Phase 2) 2019 25% Submitted 2019 (could advance to 2018)  $2,595,840  $-    $2,595,840  $2,595,840  $2,595,840  $-  
Hopkinton 606043 Signal and intersection improvements on Route 135 2019 25% Submitted 2019  $8,501,376  $-    $8,501,376  $7,860,000  $8,174,400  $(326,976)
Milford, Hopedale 607428 Resurfacing and intersection improvements on Route 16 (Main St.) 2019 25% Submitted 2019  $3,149,619  $-    $3,149,619  $2,622,962  $2,727,881  $(421,738)
Natick 605034 Reconstruction of Route 27 (North Main St.) 2019 25% Submitted 2019  $15,459,553  $-    $15,459,553  $15,459,553  $15,459,553  $-  
Everett 607652 Reconstruction of Ferry St. 2019 PRC Approved 2019 (risk)  $7,244,124  $-    $7,244,124  $15,400,000  $15,400,000  $8,155,876
Boston 605789 Reconstruction of Melnea Cass Blvd. 2019 PRC Approved 2019 (risk)  $7,853,499  $17,444,340  $25,297,839  $25,297,839  $25,297,839  $-  
Walpole (MassDOT) 602261 Reconstruction on Route 1A (Main St.) 2020 75% Submitted 2020  $18,584,373  $-    $18,584,373  $16,102,052  $17,415,980  $(1,168,393)
Lynn 602077 Reconstruction on Route 129 (Lynnfield St.) 2020 25% Submitted 2020  $4,953,270  $-    $4,953,270  $4,403,439  $4,762,759  $(190,511)
Ashland 604123 Reconstruction on Route 126 (Pond St.) 2020 25% Submitted 2020  $15,532,405  $-    $15,532,405  $13,552,165  $14,658,022  $(874,383)
Boston 606453 Improvements on Boylston St. 2020 25% Submitted 2020  $8,214,319  $-    $8,214,319  $4,971,952  $5,377,663  $(2,836,656)
Boston 606226 Reconstruction of Rutherford Ave. 2020+ PRC Approved 2021  $28,832,529  $8,578,930  $37,411,459  (see notes)   $8,578,930
Woburn 604996 Bridge replacement, New Boston St. over MBTA 2021 25% Submitted 2021  $17,784,392  $-    $17,784,392  $15,202,173  $17,100,377  $(684,015)
Beverly 608347 Intersection Improvements at 3 Locations: Cabot Street (Route 1A/97) at Dodge Street (Route 1A), County Way, Longmeadow Road & Scott Street, Mckay Street at Balch Street & Veterans Memorial Bridge (Route 1A) at Rantoul, Cabot, Water and Front Streets 2021 PRC Approved 2021 (could advance to 2020)  $3,509,576  $-    $3,509,576  $3,000,000  $3,374,592  $(134,984)
Holbrook 606501 Reconstruction of Union Street (Route 139), from Linfield Street to Centre Street/Water Street 2021 25% Submitted 2021 (could advance to 2020)  $1,363,630  $1,527,250  $2,890,880  $2,115,896  $2,380,095  $(510,785)
Framingham 608228 Reconstruction of Union Avenue, From Proctor Street to Main Street 2021 25% Submitted 2021  $10,063,912  $-    $10,063,912  $9,200,787  $10,349,634  $285,722
Norwood 605857 Intersection Improvements at Route 1 and University Avenue/Everett Street 2021 25% Submitted 2021  $6,317,236  $-    $6,317,236  $7,406,795  $8,331,636  $2,014,400
Regionwide Community Transportation  2021 n/a n/a  $1,750,000  $-    $1,750,000  $1,750,000  $1,750,000  $-  
red = delay Notes on Rutherford Ave.:
1. AC over 5 years: 2020-2024
* Year-of-expenditure figures represent current cost at an inflated rate of 4 percent per year for FFY19 and later FFYs;
**
red = increase
2. Earmarks to be applied to design
3. Estimated construction cost $120m