Comments from MassDOT Regarding Draft Amendment 1 of FFYs 2017-2021 TIP

 

Submitted November 16, 2016

We are proposing that the following repurposed earmarks be added to the current Boston FFY 2017-2021 MBTA TIP amendment out for public comment. These earmarks will be listed in the Highway element of the FFY 2017 Boston TIP, and will then be flexed to FTA.

 

Region

DEMO ID

Old Purpose of Earmark

New Purpose of Earmark

MPO Action

Type of Action

FFY

Funding Source

Federal Amount

Total (w/Match)

Notes

Boston

MA 015

Undertake improvements to South Station intermodal Station

MBTA Bus Stop Accessibility and Operational Improvements

Endorse amendment

Add project

 2017

HPP

$908,221

$1,135,276.25

Total Value of Earmarks: $1,909,696 (Federal) Repurposed Earmark; Flex to FTA

Boston

MA 170

MBTA Secure Station, Boston

MBTA Bus Stop Accessibility and Operational Improvements

Endorse amendment

Add project

 2017

HPP

$1,001,475

$1,251,843.75

Total Value of Earmarks: $1,909,696 (Federal) Repurposed Earmark; Flex to FTA

Boston

MA 133

Longwood Ave/Urban Ring Tunnel Study

MBTA Bus Stop Accessibility and Operational Improvements within the Longwood Medical Area

Endorse amendment

Add project

 2017

HPP

$129,995

$162,493.75

Repurposed Earmark; Flex to FTA

Boston

MA 199

Construct Lechmere Station area roadway and access improvements in Cambridge

Green Line Extension

Endorse amendment

Add project

 2017

HPP

$5,007,735

$6,259,668.75

Repurposed Earmark; Flex to FTA

 

The above changes would be added under Section 1C (Other Federal Aid) of the Highway element of the TIP template.

 


 

Comments from MassDOT Regarding Draft Amendment 1 of FFYs 2017-2021 TIP

 

Submitted November 17, 2016

In addition, please propose adding the following repurposed earmark as an adjustment to the Boston TIP in FFY 2017 for project #608562, SOMERVILLE- SIGNAL AND INTERSECTION IMPROVEMENT ON I-93 AT MYSTIC AVENUE AND MCGRATH HIGHWAY (TOP 200 CRASH LOCATION).

These funds are intended for the design of the project, which is currently programmed in FFY 2020 using Statewide HSIP.

 

Region

DEMO ID

Old Purpose of Earmark

New Purpose of Earmark

MPO Action

Type of Action

FFY

Funding Source

Federal Amount

Total (w/Match)

Notes

Boston

MA 128

Study and Design I-93/Mystic Ave. Interchange at Assembly Sq.

Design of Signal and intersection improvement on I-93 at Mystic Avenue and McGrath Highway.

Adjustment

Add funding source

 2017

HPP

$400,590

$500,737.50

Repurposed Earmark for Design Funds