Regional Transportation Advisory Council Meeting
November 18, 2015 Meeting
3:00 PM, State Transportation Building, Conference Room 4, 10 Park Plaza, Boston,
MA
Meeting Summary
Introductions
T. Bennett, Chair (Cambridge) called the meeting to
order at 3:00 PM. Members and guests attending the meeting introduced themselves.
(For attendance list, see page 7)
Chair’s Report–Tegin Teich Bennett, Chair
T. Bennett explained that as the incoming officers for the upcoming year,
she and Vice Chair M. Sanborn have met with past leadership and MPO Staff in
reviewing the 3C document certification process and the Advisory Council’s
role. The Officers met with MassDOT staff to explore ways to work more closely
together. T. Bennett will try to address issues that come to the Council while
they are still current and part of the discussion at the MPO level. In the near
future the Council will host a discussion on the fundamentals of the
functioning of the MPO to help members understand how the MPO works.
The consideration of funding for the Green Line
Extension was a topic at the last MPO meeting. T. Bennett asked D. Mohler,
(MassDOT) to address the Advisory Council to better understand the funding
proposals.
Green Line Extension
Project – David Mohler, Executive Director, Office of
Transportation Planning, MassDOT
D. Mohler presented an overview of the Green Line Extension project from
Lechmere to Tufts and Union Square with seven new stations, a maintenance
facility and twenty-four new light rail vehicles. The project cost was set at $1.99B
in the Full Funding Grant Agreement (FFGA) of January, 2015. Half of the
project will be funded by a federal New Starts program which is capped at $1B. Components
of the project costs are construction, right-of-way, vehicle acquisition,
professional services, design and construction oversight, and contingency funds.
The Commonwealth’s portion of the project cost is to be paid through issuance
of Special Obligation Transit Bonds.
The construction manager general contractor process (CMGC) was selected
as the procurement vehicle for completing the work on the project. This was the
first time this process was used in Massachusetts. Projected costs became
significantly larger than planned costs which led to a review of the project. Through
value engineering and redesign, MassDOT is searching for ways to bring the costs
down while other revenue options are being considered including contributions
from local and specially impacted developers, and possible MPO funding.
Currently, the project is paused pending a detailed project review.
The expectation is that the project budget will cost significantly more
than FFGA , but less than current estimates, due to value engineering efforts
now being studied. MassDOT is studying the funding gap between projected costs
and funds available and considering several options available to keep the
project viable as cancelling the project is not a desirable option. Recently,
an LRTP amendment to reallocate GLX2 to GLX1 funding was proposed to the MPO. This
amendment may be scheduled at a later MPO meeting.
On November 30, 2015, there will be a Joint Fiscal and Management
Control Board (FMCB) meeting to discuss a “look back” on the project to try to
figure out how the funding estimates were off by so much. On December 9, the
FMCB will address “the path forward”.
Questions and Comments:
D. Mohler explained the timing of asking the MPO for a reallocation of
LRTP funds from Green Line Extension - Phase Two (GLX2) to the Green Line
Extension - Phase One (GLX1) prior to the FMCB “path forward” discussion is to
establish a combined commitment to the project from its stakeholders. He
indicated a high likelihood of more funds needed even after the path forward
has been discerned. (In response to a question from T. Bennett).
As a result of the immediacy of needing to address the GLX funding gap,
D. Mohler said several staff at MassDOT are currently focusing on this issue.
(In response to a question from D. Montgomery).
D. Mohler said that in the past, bridges along the GLX line were not
built to preclude the possibility of extending the Green Line. He noted that
bridge replacement is not a main cost influence on the overall GLX budget. (In
response to a question from M. Wellons).
D. Mohler said that the construction of GLX1 would precede GLX2 which
explains the logic of asking the MPO to reallocate funds from GLX2 to GLX1. The
long-term commitment to the GLX2 project would likely be of greatest concern to
the MPO. (In response to a comment from M. Sanborn)
D. Mohler explained that time delays that might result from significant
re-design of the project would have an even more negative impact on increased
costs. Significant changes in the design of the project would also have to be
reviewed by the federal funding authority to guarantee that it meets original
requirements of the FFGA. Forcing the project to meet the available funds or
cutting back the number of stations may have an undesired effect on the project
outcomes. (In response to a comment from M. Gowing).
Minutes – October 14, 2015
A motion to approve the minutes for the October 14 meeting was
seconded. The minutes were approved.
Bicycle Network Gap:
Feasibility Evaluations, Selection of Study Locations – Katrina Crocker, Transportation Planner, CTPS
K. Crocker briefly reviewed
the 2014 Bicycle Network study which was precursor to the selection of study
locations. The goal of the study is to create a cohesive bike network, to
identify and evaluate gaps in the network; and to make recommendations for
improvements.
A gap is a lack of
connectivity between existing facilities or between a bicycle facility and a regional
transit station such as commuter rail, an MBTA station, or a key bus route. The
analysis asks if the new connection would provide connection for all trip types
such as commuter trips, work trips, and recreation trips; would it serve future
bike-pedestrian trips—and are future projected trips higher than average? The
analysis also needs to be consistent with previous plans.
The analysis produced 234 gaps
which were sorted into long (>1.5 mi.), medium (.5-1.5mi.) and short gaps
(<.5 mi.). The gaps were scored based on the existing evaluation criteria
within the three groups which resulted in high, medium and low priority gaps.
Eleven of the 36 total high priority gaps were selected for study.
Potential projects were
considered in light of MPO goals: Healthy transportation; safety and impact on
air quality based on transit; and bike and pedestrian activity. The analysis
addressed in terms of compatibility with other plans in the region and the
contribution to livability. Administrative concerns included whether the
previously identified gap was still in need of review and whether it fell in
the realm agency expertise.
Out of the top 11 high
priority gaps, three are long gaps, six are medium length gaps and two are
short gaps. The next step at the 11 locations will be to collect data, recommend
improvements, and produce a Memorandum for the MPO. Some mitigating activities
include possible route location widening, right-of-way acquisition, improved on-road
facilities, design services and providing cost estimates.
Questions and
Comments:
K. Crocker explained that consideration
of Complete Streets will be incorporated to the overall design and project
recommendations. (In response to a question from T. Bennett).
K. Crocker stated that the analysis
identified gaps between bicycle facilities and key regional transit connections
and commuter rail stops. The analysis reviewed connectivity to a municipal
center, central business district, and recreational projects.
Citing a previous study
reviewed by the Advisory Council, B. McGaw noted that regarding trip type, the
MPO give priority to work-based activity. In response to this question K.
Crocker indicated that the trip type activities covered most possible
activities including work-based activities.
K. Crocker indicated that
interest areas were used instead of desire-lines in analyzing and organizing
the best place to locate facilities in places the demand might be. She
explained the gap analysis incorporated quantitative analysis by employing GIS
methods to focus on measurable analysis points like employment density and landmark
locations. (In response to a question from D. Ernst).
K. Crocker explained that
previous plans including the LRTP Needs Assessment, the Regional Bicycle Plan
by MAPC and others were consulted in the process of the study. (In response to
a question from D. Ernst).
M. Abbott, CTPS, stated that analytical studies
conducted by CTPS take into consideration previous plans as recommendations are
formulated; this occurs not only with bike projects, but also with intersection
and corridor projects. A primary goal of the MPO is to see that studies are implemented.
All projects undertaken through the UPWP follow an organized and analytical
approach to the project selection process.
Innovative Design Guidelines
for Low-stress Bicycle Networks – Nick
Jackson, Regional Director, Toole Design Group
N. Jackson presented the newly released Separated
Bike Lane Planning & Design Guide now available on MassDOT’s website (click here). The context of the guidelines are a new in
concept and look at all standards, from the U.S. Federal government to
innovative applications in the Netherlands.
In accordance with Engineering Directive E-15-002, “This guide shall be
used by project planners and designers as a resource for considering, evaluating
and designing separated bike lanes as part of a complete streets approach for
providing safe and comfortable accommodations for all roadway users”.
The guide draws upon experience and lessons learned
from North American cities that have successfully increased bicycling while
reducing crash rates through the implementation of separated bike lanes and
other bicycle facilities.
N. Jackson defined a separated lane facility used
in the manual as having a horizontal and vertical separation from
vehicles. MassDOT is building these
facilities for purposes of achieving mode-shift goals. More attractive
facilities for more users will help reduce GHG.
N. Jackson stated that many potential bike riders are very concerned
about safety and proximity to busy traffic and find bicycling a less attractive
alternative. Several graphics depict some potential riders’ assessment of the
safety of riding on shared roadways.
The design guide focuses on bicycle safety, comfort
and connectivity. It helps to deal with
the issue of where separated bike lanes ought to go. The guide also helps to
clarify where separated bicycle lanes are appropriate and feasible.
The general design type includes sidewalk, a
sidewalk buffer, sidewalk lane, a street buffer and a street. N. Jackson gave
detail dimensions of various design types. The design guide presents graphics
and details for intersections and lanes giving special attention to issues like
passing, drainage, accessibility and landscaping. Separated bike lanes can be
integrated with transit for less air quality impacts and for greater quality of
life benefits.
The guide deals with intersection design and it
attempts to minimize the exposure to conflicts, reducing speed at conflict
points, and adding adequate sight-distance to intersections. In the U.S.,
mixing zones are used to separate traffic throughout the intersection.
The design guide includes chapters on planning,
general design considerations, intersection design, signals, and maintenance.
Questions and Comments
N. Jackson stated that the guide is determined to
be used according to MassDOT Engineering Directives. The wording is
straightforward indicating that the guideline “shall be used” by planners and
designers as a resource in evaluating and designing separated bike lanes. (In
response to a question from T. Bennett).
N. Jackson explained that community standards and
policing of shared space is a local issue which may help to explain why some
shared-lane roadways are dangerous for bicyclists to use. He mentioned that
drives and bicyclists both prefer the separated lanes as they enhance the
feeling of protection, safety and expectations of what the other operators will
do. (In response to a question from M. Murray).
M. Gowing commented that right-on-red capability is
an issue that complicates separated lanes as it makes the movements through the
intersection less predictable. N. Jackson suggested that dedicated bike signals
can help in situations like that.
O. MacDonald asked if lower volume side streets are
a preferable alternative to arterial streets. N. Jackson expressed concern that
side streets do not provide the flow and access characteristics available on
arterial streets and would diminish the attractiveness and efficiency of the
bicycle trip.
N. Jackson expressed that guidelines are in play
for the maintenance of roads for all public users and they should be shoveled
and overseen as all roads are. (In response to a question from S. Larrabee).
Old Business, New Business and
Member Announcements
M. Sanborn explained that an attendance audit will
be undertaken over the next month to monitor voting status conformity with the
recently updated bylaws. In the near future, voting and non-voting members will
be asked to help identify how the organization can be improved in terms of time
use, topic selection, and overall utility. The main goal over the next year
will be to achieve relevancy and efficient use of members’ time and energy. M.
Sanborn will seek feedback on how to keep meetings as helpful as possible and he
will keep the group informed of his findings.
T. Bennett explained that members who are having
difficulties attending meetings will be able to work with the officers to find
a way to try to improve their attendance. The Membership Committee will
continue to work on this effort.
T. Bennett announced that the former TIP, UPWP, and
LRTP Committees have been combined into one committee called the 3C
Certification Documents Committee, which will be chaired by C. Porter. The
updated committee list is online and members are encouraged to participate in
their areas of interest.
T. Bennett described how the discussion of the
Green Line Extension funding originated and asked members for their
consideration of the topic in light of today’s discussion with D. Mohler.
B. Steinberg commented that the value-engineering
being undertake now should trim off some costs as they stand today.
D. Montgomery explained that when the MPO’s GLX
discussions occurred some years ago, most of the current Advisory Council
membership were not present. The size of the project has consumed much of the
share of funding for what would otherwise go to smaller scale projects broadly
distributed throughout the MPO.
T. Bennett added that the Advisory Council’s recent
comment letter on the TIP, UPWP and LRTP expressed an interest in more
diversified, smaller projects throughout the region.
M. Gowing suggested that the “gap analysis” being
conducted by the FMCB should be weighed as there is no guarantee that the
funding gap can be filled with the MPO funds.
It was determined that a committee meeting be held
prior to the next MPO meeting. The meeting will be scheduled to further discuss
the GLX funding concern. Members will be
notified of the time and place.
J. Businger explained that a North South Station
Rail Link working group was being formed.
Adjournment
A motion to adjourn
was
made and seconded. The motion passed and the meeting
was adjourned at 4:30 PM.
ATTENDANCE
|
Municipalities (Voting) |
Attendee |
||
|
Acton |
Mike
Gowing |
||
|
Belmont |
Robert
McGaw |
||
|
Brookline |
Todd M.
Kirrane |
||
|
Cambridge |
Tegin
Bennett |
||
|
Needham |
David
Montgomery; Rhain Holland |
||
|
Westwood |
Trevor
Laubenstein |
||
|
Weymouth |
Owen
MacDonald |
||
|
Citizen
Groups |
|
||
|
AACT |
Mary
Ann Murray |
||
|
American
Council of Engineering Companies |
Fred
Moseley |
||
|
APA -
Massachusetts Chapter |
Josh
Weiland |
||
|
American
Planning Association |
John
(Tad) Read |
||
|
Association
for Public Transportation |
Barry M
Steinberg |
||
|
Boston
Society of Architects |
Schuyler
Larrabee |
||
|
Boston
Society of Civil Engineers |
Topher
Smith |
||
|
MassBike |
David
Ernst |
||
|
Massachusetts
Bus Association |
Mark
Sanborn |
||
|
National
Corridors Initiative |
John
Businger |
||
|
Riverside
Neighborhood Association |
Marilyn
Wellons |
||
|
|
|||
Agencies (Non-Voting) |
Attendee |
|
||
|
MassDOT |
David
Mohler |
||
Agencies
(Voting) |
|
|
||
|
MassRides |
Gary
St. Fleur |
||
|
Municipalities
(Non-Voting) |
|
||
|
Norwood |
Steve
Olanoff |
||
|
Guests |
|
||
|
Arthur
Strang |
Cambridge
Resident |
||
|
Ed
Lowney |
Malden
Resident |
||
|
Staff |
|
||
|
David
Fargen |
Mark
Abbott |
||
|
Maureen
Kelly |
Katrina
Crocker |
||
|
Laurenço Dantas |
|
||